LKPU analysed Dayforce’s functionality, service and contract against German HR requirements, supported the renegotiation, and implemented a P&I LOGA–Dayforce interface that satisfied both local and global needs.
The Story
A global corporation headquartered in the US, has signed a global contract with Dayforce, a full-suite HCM provider. The German HR team is hesitant to roll out as the implementation indicates major shortfalls of the solution, in both functionality and service level. LKPU conducts a detailed analysis of functionality, service and contract, enabling a rationale decision-making. To satisfy local requirements the legacy provider is kept. To satisfy global requirements, LKPU builds and implements an interface connecting P&I LOGA with Dayforce.
- Completion and prioritization of customer requirements with the local and global HR team
- Gap analysis – Dayforce contract, functionality and service level vs. Local German requirements
- Supporting re-negotiations
- Building and evaluating solution scenarios
Building and implementing the interface
Duration: 10 months