Commerzbank decided to replace the co-badge scheme on its roughly 5 million girocards with Visa Debit.

At A Glance

Commerzbank decided to replace the co-badge scheme on its roughly 5 million girocards with Visa Debit. LKPU supported Commerzbank and Bankverlag in implementing the new co-badged girocard, developed technical concepts and requirements for authorization, card management, 3DS and clearing & settlement, identified functional gaps, and prepared the technical rollout and testing phase. 

The Story

The client issues the girocard as its standard card, equipped with two schemes on one card (co-badge), and has around 5 million of these cards in circulation. Following changes in the strategic plans of the international card schemes in Germany, the client decided to replace the current co-badge scheme with an international debit scheme. The technical implementation of this new co-badged card, the so-called Combocard, was launched together with a corresponding implementation project. LKPU supported the client and its card processor in implementing the Visa Debit product to enable a timely launch. 

 LKPU supported the client with: 

  • Creation and revision of the implementation and testing plan from a technical perspective
  • Development of technical concepts for the Combocard
  • Definition of requirements for authorization and authentication, including corresponding use cases
  • Identification of functional and technical gaps, e.g. in fraud prevention and reporting
  • Planning and development of the technical rollout
  • Preparation of the testing and verification phase
  • Support of workstreams in defining key activities and initiatives in technical areas
  • Progress tracking and derivation of mitigation measures where necessary
  • Full support of the workstream for card management, 3DS and clearing & settlement, including day-to-day tasks
  • Derivation and documentation of technical requirements in these areas
  • Support in defining the technical and procedural set-up
  • Analysis and consolidation of requirement interdependencies with other workstreams.

Duration: 12 months
Teamsize: 2